Client: Thomas Bennett Community College

Architect:  Nicholas Hare Architects

Main Contractor:  Neilcott Construction Limited


Start Date:  June 2008

Completion Date: May 2009

Contract Value: £2.6M


Brief  Description:

Design and build contract for the design of a two-storey additional building adjacent to the existing secondary school. The building provides a special support center for pupils with social and communication needs and also contains a small studio theatre with changing rooms.

The structure was primarily reinforced concrete in form utilizing flat slab design to maximize floor to ceiling heights whilst minimizing the overall building height and providing an economic solution.  The reinforced concrete was partially exposed for architectural finish and the mass assisted to maintain acoustic and fire segregation between compartments of differing use.  Both the first floor and roof were of flat slab construction, which enabled the introduction of roof light without the need for visible framing and trimming beams.

As part of the environmental impact, the new building and surrounding paving and car parking required a 200,000 Litre drainage attenuation system to manage the flow of rain water into a nearby watercourse to prevent flash flooding. The new system needed to be integrated with an existing storage system which also discharged into the same watercourse and so a site wide approach was required. The use of petrol interceptors chambers was employed in car park run off areas to prevent any pollutants entering the watercourse and damaging local wildlife.









Please do not hesitate to send us an enquiry via our online form or visit the Contact Us page to obtain further information.

             You can also find us on LinkedIn

© 2015 Wareham & Associates Ltd

Company Registration Number: 4033775

Home

WAREHAM & ASSOCIATES LTD